  Below you will see an Image of the layout for the Backdrop Frames of both the Kick 'n' Score Soccer and the Slap Shot Hockey Games at Ray Rents. The Backdrop Frame is of Steel tube construction and is easily assembled by sliding  each tube and or Joint Connector by color code. Red to Red, White to White, and 
Blue
to Blue.                      See Below For Full View of Complete Frame.                           Figure 1
  1) Start out by opening up the Black Tote Case and removing and separating the contents in neatly arranged groupings of like items for easy access to assembly. After putting like items together, you're ready to make a quick inventory to ensure you'll have the correct equipment parts to assemble the game.

2) Inventory the Parts after they are laid out neatly for easy viewing. You Should have:

  • 4 each - Frame Joint Connectors of which 2 are the Top "L" Joint Connectors and 2 are the Bottom Joint Connectors.
  • 12 - Frame Tubes of which 4 are short Blue Leg Tube Sections and 8 are Red and White Frame Tube Sections.
  • 1 - Vinyl Backdrop Canvas with sewn-in Hook 'n' Loop ("Velcro") Straps.
  • Balls, Pucks, & Sticks vary between games.
  • After Inventorying items , you're ready to assemble the game.

3) Put all the Red and White Tubes into groups of pairs, Join each pair together with the White Ends facing out at each pair and the Red sides facing inward towards each other. (See Figure 2)      Figure 2

4) Build the Bottom of the Frame First. Start by laying one of your assembled Red/White Tube pairs flat one the ground. (See Figure 3)

5) Attach the two Bottom Joint Connectors to each end as shown with the white ends of Joints facing in toward each other. (See Figure 3)                                                                                    Figure 3


6) Tighten the Eye Bolts attached to the Joint Connecters securely to the Red/White Bottom Tube
(See Figures 3 & 4
)

7) Continue building the Bottom of Game Frame by sliding in all 4 of the Blue Leg Sections (Blue in Blue) to the Bottom Joint Connectors (See Figure 3) then secure each leg to Joint Connectors with the attached Eye Bolts. (See Figure 4)

8) Now you are ready to slide the Vertical Upright Side Tubes into the white openings left over in each of the two Bottom Joint Connectors. The Vertical Tubes to be inserted upright are the Red/White Frame Tube Pairs in which you've previously assembled. Secure them with the Eye Bolts provided.

9) Place both "L" Brace Joint Connectors on the tops of each Red/White Vertical Side Bar facing in toward each other. Do not fasten Eye Bolt yet. Frame Tubes must remain loose enough to slide in last Red/White Frame Tube Pair across the top horizontally. 

10) Slide in one end at a time across the Top of Game Frame into each of the two "L" Joints. Tighten Eye Bolts in the "L" Joints to the Red/White Top Tube. (See Figure 4) 
                                         
      You are now ready to Put on the Canvas Backdrop.      GO >        